Projects

#DrivingForwardOK

H.E. Bailey Turnpike

LEARN MORE

INFORMATION

  • 7.5 miles

  • Project completed Feb. 13, 2018

  • Turnpike reconstruction for lanes and safety features and toll plaza modernization for better access for PIKEPASS customers.

  • This project provides wider lanes and enhanced safety features for travel as well as improved technology for toll plaza locations for customer convenience.

DOCUMENTATION

TIMELINE

7181a5_06201bbae1c8489a9d56519d5dd89ca9.png

Feb. 13, 2018

Chickasha Toll Plaza opens. Project complete.​

7181a5_06201bbae1c8489a9d56519d5dd89ca9.png

Dec. 8, 2015

Sent Letter of Interest for consultants for Engineering Design of the relocation & rebuild of the Chickasha Toll Plaza on the H.E. Bailey Turnpike.

7181a5_06201bbae1c8489a9d56519d5dd89ca9.png

Dec. 7, 2015

Selected consultant Triad for Design Services on H.E. Bailey Turnpike reconstruction from mile markers 99 to 107.

7181a5_06201bbae1c8489a9d56519d5dd89ca9.png

Dec. 1, 2015

Authority approves Contract Modification No. 1 with Atkins on relocation of the Chickasha Toll Plaza on the H.E. Bailey Turnpike.

7181a5_06201bbae1c8489a9d56519d5dd89ca9.png

Dec. 1, 2015

Authority approves Engineering Design Services contract with Triad Design for the H.E. Bailey Turnpike rehabilitation from mile markers 99 to 107.

Oklahoma Turnpike Authority
  • Facebook - Black Circle
  • Twitter - Black Circle

Right-of-way Hotline:

1-888-312-2151

Construction Hotline:

1-405-425-7456

© 2020 by the Oklahoma Turnpike Authority.

bottom of page